When it’s No Longer Relative

1 Comment

When it’s No Longer Relative

This is a guest blog post by my colleague: Chris Waggoner. Enjoy!

Estimation of time and effort until you’re done is one of those things that every inquiring manager wants to know. In an effort to provide “accurate” estimates, companies and people spend countless hours generating list of task and debating the duration of each task. When it comes to developing software these estimates are rarely correct and often grossly wrong. The estimates are wrong because in building software that we are often building something that has never been built before. When we find ourselves being pressured to estimate something we’ve never done we tend to SWAG (PMI for Sophisticated Wild Ass Guess) the answer in man-days and/or hours without understanding or knowing all the potential variables in play. Here in lies the problem with traditional software estimation methodologies: within a short amount of time spent there are diminishing returns on effort versus value. That is to say, early in the traditional process the value of spending more time estimating doesn’t provide a higher certainty of when we will be done.

1 Comment

The Agile Project Manager—No Upfront Estimates!

The diagram represents the Cone of Uncertainty—coined by Steve McConnell of Construx. I’m sure he’s not the first or only one to reference the cone, but he famously has connected it with software development. The cone indicates the futility of estimating & committing to software projects at project initiation—not matter how well conceived the estimates are. There’s typically too much uncertainty to be accurate. Instead, an iterative or incremental approach will glean more information to improve the estimates over time. This is particularly true for projects that include new technologies, new teams, or trying to create novel or innovative products.

I’ve been managing software projects for much of my career. Early on, I spent most of my time trying to estimate projects more and more effectively. I pulled together models for how to estimate. I kept track of historical estimate vs. actual data, so that I could evaluate the quality of my estimates. I even tried some modeling or arithmetic techniques to fine tune my estimates. Some of these are quite well know techniques like Function Points or Cocomo or the Personal Software Process.

All of this was focused towards estimate quality…not software product quality. I was worrying about how to represent the time to build the software to stakeholders and accountants so that we could reasonably know how much it would cost. Then we could make better decisions around whether to start it or not.

The odd thing, at least in my experience was that no matter neither how hard we tried nor how much effort we expended on estimation and planning, over 60% of our projects went awry. They failed. They were Death Marches. They were incredibly painful. And in many cases, they resulted in people losing their jobs.

I guess my point is—accurate software project estimation is incredibly hard.